Guide · November 3, 2026

Energy and Water Permits for a Plant in Mexico: The Order They Go In, and Which Deadlines the Law Actually Sets

Ten steps, in order, to energize and supply water to a new plant in Mexico: who decides each one and which deadlines the law actually sets.

By Pedro Gloria · GP&H Legal

In short

A new plant in Mexico needs four things before it can run: a site it controls, a grid connection, water, and, if it generates or stores power on site, a permit. They do not run one after the other. They overlap, and the order in which you start them decides the timetable.

This page puts in one sequence what our guides on land, energization and water explain separately. It adds no new rules. For each step it says who decides, whether the law sets a deadline, and where the deadline comes from. Where the law sets none, we say so.

Three things to keep in mind before the table:

  1. The grid studies a site, not a deed. Moving the site later costs a new study. Choose the site first, tie it up with a contract, and buy it once the results are in.
  2. The longest items have no legal deadline: the grid studies under the new framework, the works the grid needs, and the reassignment of water rights.
  3. The model connection contract puts the infrastructure dates on you, even when the utility builds the works.

The sequence

#StepWho decidesDeadline the law setsSource
1Shortlist sites. Check water availability (aquifer or basin, if you will need your own concession), land use compatible with the process, and the land regime (no unfinished ejido conversion)Water authority; municipality; land registryNone for this stepConstitution, Art. 115(V)(d); our land guide
2Tie up the preferred site without buying it. A promise or option to purchase, in writing, for a fixed term, subject to conditions that can be verifiedYou and the sellerThe promise must be "limited to a certain time"Federal Civil Code, Arts. 2243 to 2246, 1939 and 1944 (check the local code)
3Apply to CENACE with full-operation demand, coordinates and the site's KMZ polygon. No title is required at this stage, and no generation permitCENACEFor a Load Center, the application must be handled in no more than 170 business days under the 2018 Manual, which applies insofar as it does not conflict with the new lawManual, sections 13.2.2, Tables 3 to 6, Annex IV; LSE, Art. 49; Regulation, Fourth Transitory Article
4In parallel, water. Park or utility feasibility letter with volume, validity, works and connection conditions; or, if the price includes a well, the reassignment of the rights; or a new concessionIndustrial park or water utility; National Water CommissionLetter: set by state and municipal law. Reassignment: no published timeline. New concession: 60 business days once the file is completeLAN, Arts. 22 and 37 BIS 1
5If you will generate or store on site, file the permit, in parallel and not before the studiesMinistry of Energy or CNE60 business days from receipt; simplified procedure for interconnected self-supply of 0.7 to 20 MWRegulation, Arts. 25, 27 and 58; LSE, Art. 49
6Close the purchase once the conditions are met, before asking CENACE to instruct the contractYou and the sellerNoneManual, section 12.1.3(j)
7CENACE instructs the contract. From here, no technical or non-technical modification is possibleCENACE10 business days to sign the contract, binding both the utility and the applicantLSE, Arts. 48 and 49; Manual, section 6.1.5
8Works. The utility builds them against a contribution, or you build them yourselfUtility or youNone. The model contract makes the applicant responsible for the infrastructure datesRegulation, Arts. 128 to 134; LSE, Arts. 49 and 50(IV); CNE model contract, Clauses Three, Twelve and Twenty-Six
9Inspection, CENACE order and physical connectionInspection unit; CENACE; utility72 hours from CENACE's order for the physical connectionLSE, Art. 48
10Operation: keep the water title alive. Extension requests only between three years and six months before expiryNational Water CommissionMissing the window is a waiverLAN, Art. 24

Where the time actually goes

The studies. The 170 business days in step 3 are a maximum handling period for the authority under an instrument issued before the 2025 law. They are not a promise of a result, and they do not include the time you take to complete information. One hundred seventy business days are about eight calendar months (170 divided by 5 business days a week gives 34 weeks, plus non-business days). This is approximate; check it against CENACE's calendar of non-business days.

The works. No provision sets how long the utility has to build them. A delay of more than six additional months on the infrastructure dates is a ground for terminating the contract, and the guarantee is at stake (model contract, Clauses Three and Twenty-Six). Building the specific works yourself moves the longest item from the utility's programme to yours, and no contributions are owed when you build (LSE, Art. 50(IV)).

The water. Since the December 2025 reform, buying land does not transfer the water: the authority must reassign it under Article 37 BIS 1, applicable since 9 June 2026. How that is processed, how long it takes and on what criteria it is decided is not settled. Until it is, the reassignment should be a closing condition, or the price should separate the land from the water.

Three decisions that move the timetable

DecisionWhy it matters
Request the studies before committing to the site, without waiting for the generation permitThe law says the permit may not be required to request the studies (LSE, Art. 49). Waiting for it costs time the law does not require
Give the promise to purchase a term that covers the authority's periodsThe 170 business days, plus your own time, plus a margin. If there is an extension, a fixed number of periods, not automatic and open-ended
Decide early whether to build the specific works yourselfIt is the most direct lever over the longest item, and the contract already places the risk of those dates on you

If you are buying an existing plant instead

Two rules change the sequence:

  • Water. The rights attached to the plant do not pass with the sale; they are reassigned (LAN, Arts. 22 and 37 BIS 1). Check also where each title stands in its extension window (LAN, Art. 24).
  • Foreign investment screening. Congress has approved a national security review for acquisitions of more than 49 percent of a Mexican company whose assets exceed a threshold the Commission has yet to set and whose activity includes, among others, strategic energy infrastructure and the land indispensable for its use. As of this page's cut-off it has not been published in the Official Gazette. Our foreign investment guide explains when it applies.

What remains open

  • The replacement for the 2018 Manual. If the CNE and CENACE issue new provisions, steps 3, 6 and 7 may change.
  • The practice of water reassignment and the criteria for water responsibility. Neither has published content.
  • The foreign investment reform, pending publication.

We will update this page when any of them changes.

Pedro Gloria GP&H Legal · Monterrey and Mexico City This page summarises our guides on the order of land and utility feasibility (Georgina Hernández Valencia, 22 October 2026, cut-off 3 October 2026), on energizing a plant (Pedro Gloria, 12 October 2026, cut-off 30 September 2026) and on the water concession renewal window (Pedro Gloria, 24 September 2026, cut-off 24 September 2026), and our foreign investment guide (updated 30 October 2026). It adds no rule that is not in those guides. Sources: Political Constitution of the United Mexican States, Art. 115(V); Ley del Sector Eléctrico, Official Gazette, 18 March 2025, Arts. 48, 49 and 50; Reglamento de la Ley del Sector Eléctrico, Official Gazette, 3 October 2025, Arts. 25, 27, 58, 128 to 134, and Fourth Transitory Article; Manual for the Interconnection of Power Plants and Connection of Load Centers, Official Gazette, 9 February 2018; CNE model interconnection and connection contract, Official Gazette, 17 March 2026; Ley de Aguas Nacionales as amended by the decree of 11 December 2025, Arts. 22, 24 and 37 BIS 1; Federal Civil Code, Arts. 1939, 1944 and 2243 to 2246. English renderings of Spanish legal text are ours; the Spanish original governs. Information cut-off: 2 November 2026 for the status of the foreign investment reform. For everything else, the cut-off of the guide each step comes from. GP&H Legal advises international operators on establishing and running industrial facilities in Mexico, with particular focus on the energy and water permitting that determines whether a plant can operate at all. This note is general information, not legal advice on any specific matter, and does not create an attorney-client relationship.

Have you requested the connection studies for your plant?

Describe your project to us: the site, the demand at full operation and whether there will be generation on site. A lawyer tells you which periods apply to you and which decisions to take before signing for the land.

Review your connection timetable

A lawyer replies within one business day. Sending this does not create an attorney-client relationship.

Related practice area

Energy & Natural Resources

More guides

Don't Buy the Land for Your Mexican Plant Yet. Lock the Site Until the Grid and the Water Say Yes.How Long Does It Take to Energize a Plant in Mexico? What the Law Fixes, and What It Leaves OpenMexico's New Vulnerable Activities Forms: Who Has to Register Again, and From When